Corbridge Crescent

Hackney

Brief:

TRAC Construction were appointed to construct three adjoining concrete frames, one rising to 10 storeys to create 57 homes and 5000ft of commercial space.


TRACs package of works:

• Ground remediations

• Piling

• Basement construction element

• 4 Lift cores and stair cores

• Crane logistics and lifting plan management


Logistics:
Managing on site logistics while sequencing the different stages of the 3 interlinked blocks and bordering the London Overground so careful planning and coordination was required.

23..jpg

Duration:

27 Weeks

Completed:

2020

Value:

£3,000,000

Scope:

RC Frames