Corbridge Crescent
Hackney
Brief:
TRAC Construction were appointed to construct three adjoining concrete frames, one rising to 10 storeys to create 57 homes and 5000ft of commercial space.
TRACs package of works:
• Ground remediations
• Piling
• Basement construction element
• 4 Lift cores and stair cores
• Crane logistics and lifting plan management
Logistics:
Managing on site logistics while sequencing the different stages of the 3 interlinked blocks and bordering the London Overground so careful planning and coordination was required.

Duration:
27 Weeks
Completed:
2020
Value:
£3,000,000
Scope:
RC Frames